BHP BILLITON LIMITED (ABN 49 004 028 077) (Exact name of Registrant as specified in its charter)
VICTORIA, AUSTRALIA (Jurisdiction of incorporation or organisation)
180 LONSDALE STREET, MELBOURNE, VICTORIA 3000 AUSTRALIA (Address of principal executive offices) |
BHP BILLITON PLC (REG. NO. 3196209) (Exact name of Registrant as specified in its charter)
ENGLAND AND WALES (Jurisdiction of incorporation or organisation)
NEATHOUSE PLACE, VICTORIA, LONDON, UNITED KINGDOM (Address of principal executive offices) |
Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F: [x] Form 20-F [ ] Form 40-F | ||||
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): [ ] | ||||
Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): [ ] | ||||
Indicate by check mark whether the registrant by furnishing the information contained in this Form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934: [ ] Yes [x] No | ||||
If "Yes" is marked, indicate below the file number assigned to the registrant in connection with Rule 12g3-2(b): n/a |
25 January 2007
Number 02/07
BHP BILLITON QUARTERLY REPORT ON
EXPLORATION AND DEVELOPMENT ACTIVITIES
QUARTER ENDED 31 DECEMBER 2006
This report covers the company's exploration and development activities for the quarter ended 31 December 2006. Unless otherwise stated, BHP Billiton's interest in the projects referred to in this report is 100 per cent and references to project schedules are based on calendar years.
DEVELOPMENT
The Spence (Chile) copper project was commissioned during the quarter and achieved first production in early December three weeks ahead of schedule. The budget is subject to finalisation but is expected to be within the approved budget (excluding FX impacts).
In addition, the Board approved the increased capital costs for the Ravensthorpe (Australia) nickel project to a total budget of US$2.2 billion. Lower than expected labour productivity and late delivery of some materials and equipment at Ravensthorpe means that the target date for first metal from Ravensthorpe is now the first quarter of calendar year 2008.
SHARE OF APPROVED CAPEX US$M |
INITIAL PRODUCTION TARGET DATE |
PRODUCTION CAPACITY (100%) |
QUARTERLY PROGRESS |
|
Minerals Projects |
||||
Alumar - Refinery Expansion (Brazil) Alumina |
725 |
Q2 CY09 |
2 million tpa |
Forecast costs have increased by 40% following BHP Billiton's review of the capital cost estimate and the inclusion of additional contingencies. Cost pressures are due to increases in construction, electrical, instrumentation and labour costs and general overheads. As a result the project schedule is experiencing delays and we expect commissioning to occur in the second quarter of CY09. |
PROJECT AND OWNERSHIP |
SHARE OF APPROVED CAPEX US$M |
INITIAL PRODUCTION TARGET DATE |
PRODUCTION CAPACITY (100%) |
QUARTERLY PROGRESS |
Copper |
990 |
Q4 CY06 |
200,000 tpa copper cathode |
Completed three weeks ahead of schedule. Budget is subject to finalisation but is expected to be within the approved budget (excluding FX impacts). |
Western Australia Iron Ore (Australia) -RGP3 Iron Ore |
1,300 |
Q4 CY07 |
20 million tpa |
On schedule and budget. Engineering and procurement activities were essentially completed during the quarter with construction activities now 35% complete. |
Samarco Third Pellet Plant (Brazil) Iron Ore |
590 |
1H CY08 |
7.6 million tpa |
On schedule and budget. First steel was erected at the Pellet Plant at Ubu and 50% of the pipe for the pipeline has been installed. Overall the project is 49% complete. |
Koala Underground (Canada) Diamonds |
200 |
End CY07 |
3,300 tonnes per day ore processed |
On schedule and budget. Procurement is well advanced and engineering is nearly complete. |
Ravensthorpe (Australia) Nickel |
2,200 |
Q1 CY08 |
Up to 50,000 tpa contained nickel in concentrate |
On revised schedule and budget. Construction is approximately 78% complete with engineering and procurement activities finalised during the quarter. |
Nickel |
556 |
Q1 CY08 |
45,000 tpa nickel |
On schedule however the budget has been revised. Expansion was essentially mechanically complete at the end of December 2006. |
Petroleum Projects |
||||
Oil/Gas |
1,500 |
Under review, forecast 2H CY07 |
200,000 barrels of oil and 180 million cubic feet of gas per day |
Cost and schedule remain under review but we estimate a capital cost of approximately US$1.5 billion to plateau production from 11 wells compared to the previous estimate of approximately US$1 billion, a 50% increase. Development costs from plateau production for the full life of the field remain subject to finalisation. Six development wells have been drilled with five being completed at the end of December. The Balder installation vessel is undergoing repair as publicly reported by Heerema. |
North West Shelf Train 5 LNG |
300 |
Late CY08 |
LNG processing capacity of 4.2 million tpa |
On schedule and revised budget as advised by the Operator. Preassembled units from the construction site in Indonesia have begun arriving on site. The major mechanical erection contractor is on site and has begun work. |
Neptune (US) Oil/Gas |
300 |
End CY07 |
50,000 barrels of oil and 50 million cubic feet gas per day |
On schedule however the project is experiencing some cost pressure. Drilling was completed for the first two of the seven development wells. |
Stybarrow Oil/Gas |
300 |
Q1 CY08 |
80,000 barrels of oil per day |
On schedule however the project is experiencing some cost pressure. Two injection wells were successfully completed and three development wells have been drilled. The FPSO has completed sea trials. |
North West Shelf Angel (Australia) Oil/Gas |
200 |
End CY08 |
800 million cubic feet gas per day |
On budget and schedule. Fabrication of topsides and the jacket are progressing to plan. All major contracts have now been let. |
Shenzi (US) Oil/Gas |
1,940 |
Mid CY09 |
100,000 barrels of oil and 50 million cubic feet gas per day |
On budget and schedule. Drilling of the first development well was completed and fabrication of the topsides and hull continued. |
MINERALS EXPLORATION
BHP Billiton continued to pursue global exploration opportunities for key commodities of interest utilising both in-house capabilities and the Junior Alliance Programme.
Grassroots exploration continued on diamond targets in Angola, Canada and the Democratic Republic of Congo (DRC), on copper targets in Mexico, Chile, Mongolia and the DRC; and on nickel targets in Australia, Russia and Africa. Exploration for iron ore, coal, potash and bauxite was undertaken in a number of regions including Australia, Brazil, Canada and West Africa.
For the half year ended 31 December 2006, BHP Billiton spent US$153 million on minerals exploration, of which US$111 million was expensed. Capitalised exploration included US$41 million for the Olympic Dam Expansion.
PETROLEUM EXPLORATION
Exploration and appraisal wells drilled during the quarter or in the process of drilling as at 31 December 2006.
WELL |
LOCATION |
BHP BILLITON EQUITY |
STATUS |
Persephone-1 |
Dampier sub-basin Western Australia |
16.67% BHP Billiton; Woodside operator |
Hydrocarbons encountered. More appraisal required. Plugged and Abandoned. |
Shenzi-6 |
Gulf of Mexico, Green Canyon |
44% BHP Billiton and operator |
Drilling ahead. |
Ruby-1 |
Trinidad and Tobago, Block 3 (a) |
25.5% BHP Billiton and operator |
Temporarily abandoned. Encountered approximately 1,200 feet TVD (gross) of hydrocarbon-bearing sands with more than 800 TVD feet of net pay. The well tested at a rate of nearly 5,000 barrels of oil per day through a 7/8th-inch choke. See news release dated 2 November 2006. |
Ruby-2 |
Trinidad and Tobago, Block 3 (a) |
25.5% BHP Billiton and operator |
Drilling ahead. |
Torosa-1 |
Browse Basin |
8.33% BHP Billiton, Woodside operator |
Hydrocarbons encountered. More appraisal required. Plugged and Abandoned. |
Torosa-3 |
Browse Basin |
8.33% BHP Billiton, Woodside operator |
Hydrocarbons encountered. More appraisal required. Plugged and Abandoned. |
Petroleum exploration expenditure for the half year ended 31 December 2006 was US$159 million. The amount expensed was US$154 million including US$43 million of exploration expenditure previously capitalised.
Further information on BHP Billiton can be found on our Internet site: www.bhpbilliton.com
Australia Jane Belcher, Investor Relations |